Capacity Planning When People Are on Leave

Why allocation percentages overstate team capacity, and how to plan around leave and shared people, with the checks software delivery intelligence uses.

Updated · All guides

The short answer

Capacity is the time people actually have, not the percentage they are allocated. For each person, start from their contracted capacity, subtract approved leave in the planning window, add up their allocation across every project, and compare the two. Anyone above about 85% of their available time is at risk; anyone above 100% is overloaded. Check people one by one, because team totals hide individual overload.

Why allocation percentages overstate capacity

A worked example

A team of five, planning the next four weeks (20 working days). Allocation is each person's total across all their projects.

Person Contracted capacity Approved leave Available Allocated Load
Asha100%0 days100%90%90%: at risk
Ben100%5 days75%80%107%: overloaded
Chen60% (part time)0 days60%60%100%: at risk
Dana100%10 days50%100%200%: overloaded
Eli100%0 days100%40%40%: room to help

Available = contracted capacity × (1 − leave days ÷ working days in the window). Load = allocated ÷ available.

The allocation sheet alone says nobody is above 100%. Adding leave changes the picture: Dana has half the time their allocation assumes, Ben is slightly over, and Eli has room to take work from both. Add the team up instead and you get 370% allocated against 385% available, about 96%, which looks fine and hides all of it.

The thresholds to use

LoadStatusWhat it means
Under 50%Under-usedRoom to take work from overloaded colleagues or start the next thing.
50–84%HealthyEnough slack for support work, meetings and surprises.
85–100%At riskFully booked. Any unplanned work pushes something out.
Over 100%OverloadedMore work than time. Something will slip; decide what, before it does.

Planning people to 100% is the most common mistake. Software work always includes interruptions: production issues, reviews, questions from other teams. 85% leaves room for them.

What to do when someone is overloaded

  1. Move work to someone under-used with the right skills, like Eli in the example.
  2. Move dates for the lower-priority project, and tell its stakeholders now rather than at the deadline.
  3. Reduce the number of projects a person is spread across. Switching between four projects costs more than the allocation shows.
  4. Feed it into the forecast. Lost capacity pushes delivery dates out; see how to forecast a delivery date from Jira.

Where the data lives

Capacity planning is hard mostly because the inputs sit in different places. Jira knows who is assigned to which issues. Allocation across projects usually lives in a spreadsheet or resource plan. Leave sits in an HR system or a shared calendar. Each is accurate on its own; the overload only shows when they are combined, per person, for the same window.

Practical habits that help:

How Exentras handles capacity

Exentras brings allocation, leave and project data together. Team capacity shows each person's allocation across all projects against their own capacity, which can be set below 100% for part-time staff, using the same bands: under 85%, 85–100% and over 100%. Approved leave over the next 30 days reduces each person's effective capacity, so you see who is really available.

Overload also feeds the rest of the product: it is one of the signals in each project's risk score and delay forecast. Team capacity is included in the Growth and Enterprise plans. On Enterprise, portfolio capacity alerts also flag anyone who is overloaded, or whose approved leave leaves them short of the time their allocation needs. See pricing.

Frequently Asked Questions

What is a healthy allocation level for a software team member?

Below about 85% of their available time. Between 85% and 100% there is no slack for support work, meetings or surprises, and above 100% the person is overloaded and something will slip.

How should leave be included in capacity planning?

Subtract approved leave from each person's available time for the planning window before comparing it with their allocation. Two weeks off in a four-week window halves that person's capacity, even if their allocation sheet still says 100%.

How do part-time people fit into capacity planning?

Give each person a capacity that reflects their contract, for example 60% for three days a week, and measure their allocation against that rather than against 100%.

Does Exentras account for leave in team capacity?

Yes. Team capacity shows each person's allocation across all projects against their capacity, and reduces their effective capacity for approved leave over the next 30 days. Overload also feeds each project's risk score and delay forecast.